General Information

If you are planning to carry out building work that needs to be checked by a building control body you can choose either of the following routes:

  1. submit an application for building control approval with full plans (described in Regulation 14 of the Building Regulations 2010).
  2. submit a building notice, which contains less information than full plans (see Regulation 13 of the Building Regulations 2010).

It is necessary to deposit an application for building control approval with plans instead of a building notice if any of the following work is proposed:

  • building work in relation to a building to which the Regulatory Reform (Fire Safety) Order 2005 applies or will apply after building work is complete – examples of such buildings include:
    • hotels and boarding houses
    • offices, shops and factories
    • flats – if there is more than one flat and the work affects the common parts (areas shared with other flats, for example, entrance corridors, hallways or stairs)
  • building work that includes erecting a building that fronts a private street
  • building work that involves building over or otherwise interfering with an existing shared drain, sewer or disposal main shown on a map of sewers
When you can start building works (not including higher-risk building projects)

Once you have submitted a Building Notice application or Full Plans application, work can start on site 48 hours (2 working days) after notice has been given to Warwick District Council (Warwick BC) of your intention to start building.

Please remember that you must tell Warwick District Council (Warwick BC) when inspection stages are reached so that a surveyor can inspect the works as they go along.